The Dutch programme is built like a test plan, not a demonstration. Six pilots work outwards from the gate in a deliberate order, and two of them are addressed to the whole European network rather than to the Netherlands.

It starts inside the country. The first pilot tests the connection between Dutch authorities’ user applications and the Dutch eFTI-Gate, with a set of test cases covering both happy flows and edge cases, and feedback to each authority on which cases passed, failed or were not tested — in effect a readiness scorecard for authorities building their own applications. The intention is to keep the setup operational after the pilot so that any Dutch authority can develop and test against it. Then it goes outward: gate-to-gate validates cross-border retrieval, routing, authentication and authorisation with at least one other Member State, including edge cases such as a missing dataset or an unreachable gate; gate-to-platform turns to the economic operator side, testing whether platforms can generate, store and expose realistic datasets through a UIL or QR code and whether the gate correctly rejects invalid or incomplete data.

The last three widen the lens. BDI connects the Dutch Basic Data Infrastructure to the eFTI environment so that data created in business-to-business processes can populate regulatory datasets without a parallel reporting system. And two performance tests — response times and search functionality — invite authorities, platforms and gates across the EU to measure the network under load before go-live in mid-2027.

Lead beneficiary

Ministry of Infrastructure and Water Management, the Netherlands

Countries involved

The Netherlands, with at least one other Member State for gate-to-gate testing, and EU-wide participation invited for the two performance tests

Transport modes

Road, inland waterways, rail, air and waste, depending on the cooperation of authorities and operators. The gate-to-gate and performance pilots are transport-mode independent

Main stakeholders

Ministry of Infrastructure and Water Management · Human Environment and Transport Inspectorate (ILT) and the Dutch Police, preferably, as frontrunners, subject to further agreements being made · other Dutch authorities · the National Road Traffic Data Portal as IT supplier of the Dutch gate · other Member States' gates and their IT suppliers · Dutch economic operators and eFTI service providers · all authorities, platform providers and gates subscribing to the performance tests.

eFTI components

eFTI Gate throughout. eFTI Platform, AAP, Registry of identifiers and CA application vary by pilot, several of them optional depending on availability

Timeline

May 2026 – June 2027 across the six pilots, with the two performance tests possibly repeated yearly after go-live

Pilot type

Mixed. The first pilot is authority-focused, the gate-to-gate pilot focuses on neither platform nor authority but on the gate-to-gate connection, the gate-to-platform pilot is platform-focused with authorities not participating directly, BDI2eFTI is an economic operator pilot, and the two performance tests are addressed to authorities, platforms and gates alike
  • Test the connection between Dutch authorities and the national eFTI-Gate, test all aspects of the authority access point functionality, and let authorities validate the correct behaviour of their user applications.
  • Validate gate-to-gate communication with at least one other Member State, including UIL-based cross-border dataset retrieval and authentication and authorisation between gates.
  • Validate that the Dutch gate can request and receive datasets from eFTI platforms, that datasets are correctly validated against the eFTI data model, and that invalid or incomplete datasets are rejected appropriately.
  • Establish a technical interface between the Basic Data Infrastructure and an operational eFTI platform, mapping BDI data models to eFTI datasets in accordance with Regulation 2020/1056.
  • Provide a repeatable performance measure of the eFTI network — response times and search throughput — identifying potential bottlenecks before go-live in mid-2027 and monitoring network health afterwards.
Integration NL Authorities

authentication and authorisation with valid and invalid credentials, dataset requests by UIL, search requests with different identifier combinations, and validation of the behaviour of user applications and the gate in happy flows and edge cases. Piloting September 2026.

Gate-to-Gate Integration Pilot (NL Gate2Gate)

gate-to-gate authentication and trust validation, cross-border UIL lookup, routing and dataset retrieval, edge cases such as a missing dataset or unreachable gate, and logging and audit trail across both Member States. Piloting November 2026.

Gate-to-Platform Integration Pilot (NL G2P)

submission of a dataset by an economic operator and its retrieval by the Dutch gate, dataset validation, rejection of incorrect or incomplete data, handling of connectivity issues, UIL generation and the search mechanism. Piloting January 2027.

BDI eFTI Interoperability Pilot (BDI)

creation of transport data within a BDI-enabled business process, storage of regulatory data on an eFTI platform, UIL and QR generation, and retrieval by a competent authority through the full access chain. Piloting Q4 2026.

Performance Test – Response Times

measuring response times between gate and authority, between two gates, and between gate and platform, for dataset requests by UIL, search requests and delivery of authority feedback. Piloting March 2027, possibly repeated yearly.

Performance Test – Search Functionality

measuring throughput and delay for deliberately broad searches — all datasets from a Member State, all datasets with dangerous goods, automated searches on large lists of licence plates — performed by one or many authorities in one or many Member States. Piloting May 2027.

The national pilots expect concrete artefacts: guidelines for testing the user applications connected to the gate and a progress report authorities can use to monitor and validate their readiness; a fully validated gate-to-gate interoperability setup, a cross-border test setup for future EU pilots and verified readiness of the Dutch gate for national and international operations; and a validated gate-to-platform setup usable by all Dutch economic operators. BDI2eFTI expects validated interoperability between the two ecosystems, a reusable BDI-to-eFTI mapping framework and recommendations for scaling it across Member States.

The two performance tests aim first at a system for detecting bottlenecks and large delays early enough to improve the network before it becomes operational in mid-2027, and then at periodically monitoring network health after go-live, informing each party about the responsiveness of its own component without shaming and rewarding the top performers. The search test is also expected to lead to recommendations on restrictions for the search functionality, since unrestricted general searches could generate loads comparable to a denial-of-service attack.